A bridge replacement took place at Uberlandia, MG on September 01, 2007 TAKRAF crane GTK 970001-3E of FCA lifting one side of a steel bridge part above Floriano Peixoto Avenue at 10:17hrs The first part of the rail overbridge lies on the ground in Uberlandia yard 150 minutes later The second half of the bridge in the air at 18:06hrs as light starts to fade The crane turns to swing the bridge section around at 18:09hrs Loading the section onto a flat wagon at 18:14hrs The new bridge part arriving above the pillars at 20:03hrs Thanks to Johannes J Smit for these shots Return to the Brazil Gallery Index page